The deal in plain words
On June 22, 2026, Chevron and Microsoft announced a 20-year power purchase agreement. A Chevron subsidiary is to develop a natural-gas power plant in West Texas, rated at 2.67 gigawatts, to supply a Microsoft-operated data center. The project is called Project Kilby. The plant is planned in phases, with most of its turbines from GE Vernova and the rest from Solar Turbines, a Caterpillar company.
- Status: announced, not built. Oil & Gas Journal reports a final investment decision is due by the end of 2026, with first power in 2028.
- Cost: not disclosed. Chevron says the project is already counted in its 2026 financial guidance.
- Water: plans to use non-potable brackish groundwater rather than fresh water.
What we could not confirm
Some summaries say this plant will include carbon capture. In the two reports we checked (TechCrunch and Oil & Gas Journal), carbon capture is not mentioned for this plant; the Oil & Gas Journal describes only controls for nitrogen oxide air pollution. We are not claiming carbon capture until a primary source says so. If you have one, tell us.
It is not only Chevron
Oilprice.com (November 8, 2026) describes a wider pattern. Among its examples: a gas-fired plant under construction in Texas for Amazon, and an August announcement by Nvidia, SoftBank and the U.S. government for a large fossil-fuel plant to power an OpenAI project in Ohio. Details and figures for those projects vary by source, so check the original reports before relying on them.
The case in favor
- AI data centers need steady power around the clock, and gas plants can supply it while the grid catches up.
- A 20-year contract gives both sides price and supply certainty.
- Energy companies already know how to build and run large power and pipeline projects.
The case against
- The Environmental Integrity Project estimates the plant could emit more than 13 million tons of carbon dioxide, plus air pollutants (reported by TechCrunch).
- TechCrunch notes Microsoft has pledged to eliminate its carbon emissions by 2030, and says this plant will make that goal harder.
- A peer-reviewed study in npj Climate Action, cited by Oilprice, estimates AI-enabled gains in fossil fuels could add 0.47 to 1.8 billion metric tons of CO2 a year.
Our take (opinion, not fact)
The software gets the headlines, but the limit on AI growth is increasingly physical: power, grid connections and the companies that supply them. That raises fair questions about who captures the value of the AI buildout, and where new jobs and capital spending land. The facts above do not settle whether this is good or bad. That depends on whether the plant is built, how it is run, and what it emits.
Sources
Corrections welcome. This page summarizes public reporting in our own words and is not investment, legal or financial advice.